Projects
Resource hub
Brisbane 2032: the construction program, tracked
19 venues, villages and transport projects, the twice-yearly Queensland Construction Outlook, the milestones as they land, and every story we publish on the road to the Games.
Queensland Construction Outlook · September 2026 edition
Queensland Construction Outlook: 2032 and Beyond
Construction and infrastructure outlook for Brisbane and South East Queensland to the 2032 Olympic and Paralympic Games
Where the 2032 venue, village and transport program stands at September 2026, who is building it, and why market capacity — not project demand — is the constraint that decides whether it lands on time.
Published · Research cut-off 15 September 2026 · 26 min read · Next edition March 2027
- 17
- New or upgraded venues
- seven new, ten upgraded (GIICA)
- $7.1bn
- Venues funding envelope
- state and federal, plus $3.5bn for villages
- $75bn
- Queensland pipeline peak
- in 2027–28 (CSQ)
- 35,000
- Peak workforce shortfall
- statewide, 2027–28 (CSQ)
- ~8,000
- Games construction workforce
- at the 2030–31 venue-and-village peak
- $19bn+
- Cross River Rail
- first passenger services expected 2029 (QAO)
Articles
Latest 2032 coverage
Project highlights
The 2032 project register
Every Games-critical venue and village plus the transport programs that share its workforce, with status as at the current edition’s research cut-off. A project’s latest story appears on its card as it is published.
Brisbane venues and villages
The Victoria Park precinct, the Showgrounds village and the Woolloongabba arena — the program's centre of gravity.
New venue
Brisbane Stadium
Victoria Park, Brisbane
3/5 · Early works
New 63,000-seat oval stadium for the ceremonies and athletics; long-term home for cricket and AFL.
- Design:
- COX Architecture, Hassell, Azusa Sekkei
- Delivery:
- Built–SACYR (ECI); John Holland–BESIX Watpac (ECI)
- Main works:
- 2027
Where it standsHide detail
Status. Principal architects appointed; field-of-play and location resolved; design continuing with fan experience, precinct and transport interfaces under development.
Delivery. Initial works began 1 June 2026. Two joint ventures are in competitive Early Contractor Involvement; the final builder follows the ECI process, with main construction targeted from 2027.
Outlook. Advancing but high-risk. Site and design leadership are established; cost, transport, park interfaces, ground conditions and schedule integration remain critical.
New venue
National Aquatic Centre
Spring Hill, Brisbane
3/5 · Early works
Elite aquatics complex adjoining Centenary Pool; permanent capacity around 8,000, Games-mode capacity 25,000.
- Design:
- ARM Architecture, NH Architecture, Arkhefield
- Main works:
- 2027
Where it standsHide detail
Status. Design team appointed; design progressing in parallel with contractor procurement.
Delivery. Site possession and initial works from 1 September 2026. Four contractors shortlisted in July; a two-party ECI and preferred-contractor selection are expected in early 2027.
Outlook. Advancing. Heritage integration, pools technology, temporary seating, the roof solution and simultaneous procurement and design are the key controls.
Village
Brisbane Showgrounds and Athletes Village
Bowen Hills, Brisbane
3/5 · Early works
Main village for more than 10,000 athletes and officials across about 1,800 apartments, plus a Main Arena uplift and post-Games housing.
- Design:
- Woods Bagot, Cottee Parker, DBI, Plus Studio, Howells
- Delivery:
- Lendlease (partner)
Where it standsHide detail
Status. Design collective appointed. Early works and arena design activities began after the 2025 Ekka.
Delivery. Project partners Lendlease and the RNA. Delivery combines precinct works, residential construction, showgrounds operations and conversion planning.
Outlook. Moderate-to-high interface risk. Strong partners and design mobilisation are positive; the constrained operating site, event calendar and conversion program require detailed staging.
Precinct
Gabba Entertainment and Housing Precinct
Woolloongabba, Brisbane
1/5 · Planning
Proposed 17,000-seat indoor arena inside a housing-dominant redevelopment.
Where it standsHide detail
Status. Site investigations under way from March 2026; commercial and early-works activity progressing with the private sector.
Delivery. The 2026–27 budget provides $45.6 million over two years for early works and a competitive market process.
Outlook. Earlier maturity than the core venues. Private finance, mixed-use feasibility and the Cross River Rail and precinct interfaces are the principal uncertainties.
Venue upgrade
Queensland Tennis Centre
Tennyson, Brisbane
1/5 · Planning
Permanent practice-court and facility upgrades, with Games overlay and accessibility requirements.
Where it standsHide detail
Status. One of the ten upgraded venues; project validation and investment decisions still required.
Delivery. No principal delivery contractor publicly confirmed.
Outlook. Planning stage. Scope control and venue-operation staging will determine schedule pressure.
Venue upgrade
Chandler Sports Precinct program
Chandler and Belmont, Brisbane
1/5 · Planning
Upgrades to the precinct, Brisbane Aquatic Centre, Anna Meares Velodrome and the BMX centre; a new Para Sport Facility; shooting-centre works at Belmont.
Where it standsHide detail
Status. Projects at differing validation, concept and design stages; the precinct must integrate multiple operating venues and Games overlays.
Delivery. No complete set of head contractors publicly confirmed.
Outlook. Portfolio interface risk. Several smaller projects can become schedule-critical if procured late or delivered concurrently inside an active precinct.
South East Queensland venues
New indoor centres, the whitewater venue and the Sunshine Coast stadium — medium projects drawing on the same trades as the flagships.
New venue
Moreton Bay Indoor Sports Centre
Petrie, Moreton Bay
3/5 · Early works
New 12-court multi-use indoor centre for community sport and wheelchair rugby.
- Design:
- Populous
- Main works:
- 2027
Where it standsHide detail
Status. Design and planning progressing; council undertaking early site works.
Delivery. Construction anticipated from 2027.
Outlook. Advancing. Large building-services, structural, façade, fit-out and sports-equipment demand north of Brisbane.
New venue
Logan Indoor Sports Centre
Logan
3/5 · Early works
New nine-court accessible centre with a Games capacity of 7,000.
Where it standsHide detail
Status. Demolition and site-preparation works began in February 2026.
Delivery. Head contractor not publicly confirmed.
Outlook. Advancing. Adds southern-Brisbane demand for indoor-sports trades and specialist equipment.
New venue
Redland Whitewater Centre
Birkdale, Redlands Coast
2/5 · Procurement
New specialist whitewater venue.
Where it standsHide detail
Status. In procurement and delivery; the 2026–27 budget supports commencement alongside the stadium and aquatic centre.
Delivery. Head contractor not publicly confirmed.
Outlook. In procurement. Specialist hydraulic, earthworks, concrete, pumping, electrical and water-treatment supply chain.
Venue upgrade
Sunshine Coast Stadium
Bokarina, Sunshine Coast
2/5 · Procurement
Upgrade to host up to 20,000 Games spectators — grandstands, amenities and supporting facilities.
- Design:
- Architectus, HKS
- Main works:
- 2027
Where it standsHide detail
Status. Architect appointed; design continues through 2026.
Delivery. Early-works contractor EOI closed September 2026; site preparation planned before the end of 2026 and main construction from 2027.
Outlook. Advancing. Contributes to the Sunshine Coast's simultaneous 2030–31 labour peak and competes with The Wave and housing.
New venue
Sunshine Coast Mountain Bike Centre
Maroochy River, Sunshine Coast
2/5 · Procurement
New permanent mountain-bike venue.
Where it standsHide detail
Status. Listed by the 2026–27 budget as in procurement and delivery.
Delivery. Head contractor not confirmed.
Outlook. In procurement. Civil, landscape, environmental, trail-building and temporary spectator infrastructure.
Regional venues
Cairns, Rockhampton and Toowoomba — Games work that spreads demand beyond the south-east.
Venue upgrade
Barlow Park Stadium
Cairns
3/5 · Early works
New western grandstand, permanent seating from about 1,700 to 5,000, amenities and athlete facilities.
- Design:
- Architectus
- Main works:
- mid-2027
Where it standsHide detail
Status. Preliminary design under way; delivery-contractor prequalification commenced July 2026.
Delivery. Services relocation from September 2026; demolition and site preparation late 2026; main construction expected from mid-2027.
Outlook. Advancing. Regional mobilisation and accommodation add cost, while delivery spreads demand beyond SEQ.
Venue upgrade
Toowoomba Showgrounds
Toowoomba
1/5 · Planning
Equestrian venue upgrade.
Where it standsHide detail
Status. Part of the authority upgrade program; validation and investment decisions continue.
Delivery. Contractor not confirmed.
Outlook. Planning stage. Regional contractor participation reduces SEQ concentration but competes with Toowoomba's broader pipeline.
Venue upgrade
Rockhampton Flatwater Facility
Fitzroy River, Rockhampton
1/5 · Planning
Flatwater venue upgrade on the Fitzroy River.
Where it standsHide detail
Status. Included in the authority's upgraded-venue portfolio.
Delivery. Contractor not confirmed.
Outlook. Planning stage. Marine, river, civil, environmental and temporary-overlay packages.
Transport and rolling stock
Games-enabled rail, road and fleet programs that compete for the same engineers, operators and materials.
Rail
Cross River Rail
Inner Brisbane
5/5 · Commissioning
The backbone project for inner-Brisbane rail capacity: twin tunnels, new underground stations and ETCS signalling.
- Delivery:
- PULSE (Pacific Partnerships, CPB, UGL, DIF, BAM, Ghella); UNITY (CPB, UGL, AECOM, Jacobs); Sequence Alliance (Hitachi Rail, Queensland Rail)
Where it standsHide detail
Status. Total cost to exceed $19 billion; first passenger services expected in 2029 (QAO, December 2025).
Delivery. Critical path has shifted from bulk civil works to integration, testing, signalling and operational readiness.
Outlook. Under delivery. Civil completion without operational readiness is the risk; commissioning is its own critical path.
Latest
Cross River Rail is in testing — and the certification phase alone takes two yearsRail
Logan and Gold Coast Faster Rail
Kuraby to Beenleigh
3/5 · Early works
$5.75 billion capacity expansion between Kuraby and Beenleigh, intended for completion before 2032.
- Delivery:
- ActivUs (ACCIONA, CPB Contractors, UGL, SMEC, WSP)
Where it standsHide detail
Status. Major-works alliance formed; site establishment and early works planned for the first half of 2026.
Delivery. One of the clearest contractor structures in the pipeline and beyond preliminary procurement.
Outlook. Under delivery. Competes directly with The Wave and remaining Cross River Rail systems work for specialist rail personnel.
Rail
The Wave (Sunshine Coast rail)
Beerwah to Caloundra
3/5 · Early works
Stage 1: 19 km of dual-track rail, stations at Aura and Caloundra, and Beerwah station upgrades.
- Delivery:
- Beerwah Coast Connect (Georgiou, Hatch, Laing O'Rourke); CoastalTraX (ACCIONA, Georgiou); Alstom and UGL (ETCS)
- Main works:
- early 2027
Where it standsHide detail
Status. Design and pre-construction packages awarded May 2026; detailed design and investigations continue into 2027.
Delivery. Major construction expected from early 2027, subject to environmental approvals.
Outlook. Advancing. Makes the Sunshine Coast a market-capacity hotspot: rail, stadium, village and housing peak together.
Rolling stock
Queensland Train Manufacturing Program
Torbanlea and Ormeau
4/5 · Main works
65 six-car trains, the Torbanlea manufacturing facility and the Ormeau rail facility under a design-build-maintain contract.
- Delivery:
- Downer
Where it standsHide detail
Status. Supports SEQ growth, Cross River Rail and 2032 readiness.
Delivery. All 65 trains intended to be on the network by 2032.
Outlook. Under delivery. Fleet, depot and layover capacity are part of the Games-time transport requirement, not an add-on.
Road
Coomera Connector Stage 1
Gold Coast
4/5 · Main works
New north–south road link improving Gold Coast network resilience, delivered in north, central and south packages.
- Delivery:
- ACCIONA–Georgiou; Seymour Whyte; Fulton Hogan
Where it standsHide detail
Status. Under construction across the packages.
Delivery. ACCIONA–Georgiou (north), Seymour Whyte (south main works), Fulton Hogan (central).
Outlook. Under delivery. Extends demand for bulk earthworks, structures, pavements, plant operators and materials through the pre-Games period.
Announcements
Milestones on the road to 2032
Recent
September 2026
National Aquatic Centre site works begin; Sunshine Coast Stadium early-works EOI closes; Barlow Park services relocation starts
August 2026
Victoria Park draft legacy plan released for consultation (3 August to 27 September)
July 2026
Four contractors shortlisted for the National Aquatic Centre; Barlow Park delivery-contractor prequalification opens
1 June 2026
Initial works commence at Brisbane Stadium, Victoria Park
May 2026
The Wave Stage 1 design and pre-construction contracts awarded
April 2026
Brisbane Stadium ECI shortlist: Built–SACYR and John Holland–BESIX Watpac
February 2026
Logan Indoor Sports Centre demolition and site preparation begin
December 2025
QAO: Cross River Rail to exceed $19 billion, first passenger services expected 2029
August 2025
Early works and Main Arena design begin at Brisbane Showgrounds after the Ekka
25 March 2025
GIICA's 100 Day Review and the 2032 Delivery Plan: venues consolidated at Victoria Park
Ahead
Late 2026
Barlow Park demolition and site preparation; Sunshine Coast Stadium site preparation
Early 2027
National Aquatic Centre preferred contractor; The Wave major construction (subject to approvals); final Victoria Park legacy plan
2027
Main construction starts at Brisbane Stadium, Moreton Bay Indoor Sports Centre and Sunshine Coast Stadium; Barlow Park from mid-year
2027–28
Queensland pipeline peaks near $75 billion; statewide workforce shortfall peaks at up to 35,000 (CSQ)
2028
Construction Tech TAFE Centre of Excellence facilities at Caloundra and Moreton Bay due
2029
Cross River Rail first passenger services expected
2030–31
Games venue-and-village labour demand peaks near 8,000 workers
2031
Readiness year: test events, overlay, security and accessibility rehearsals
23 July 2032
Brisbane 2032 Olympic Games open (Paralympic Games from 24 August)


