Brisbane 2032: the construction program, tracked

19 venues, villages and transport projects, the twice-yearly Queensland Construction Outlook, the milestones as they land, and every story we publish on the road to the Games.

The reportCoverageProject registerMilestones

Queensland Construction Outlook · September 2026 edition

Queensland Construction Outlook: 2032 and Beyond

Construction and infrastructure outlook for Brisbane and South East Queensland to the 2032 Olympic and Paralympic Games

Where the 2032 venue, village and transport program stands at September 2026, who is building it, and why market capacity — not project demand — is the constraint that decides whether it lands on time.

Published · Research cut-off 15 September 2026 · 26 min read · Next edition March 2027

17
New or upgraded venues
seven new, ten upgraded (GIICA)
$7.1bn
Venues funding envelope
state and federal, plus $3.5bn for villages
$75bn
Queensland pipeline peak
in 2027–28 (CSQ)
35,000
Peak workforce shortfall
statewide, 2027–28 (CSQ)
~8,000
Games construction workforce
at the 2030–31 venue-and-village peak
$19bn+
Cross River Rail
first passenger services expected 2029 (QAO)

Articles

Latest 2032 coverage

All projects

Project highlights

The 2032 project register

Every Games-critical venue and village plus the transport programs that share its workforce, with status as at the current edition’s research cut-off. A project’s latest story appears on its card as it is published.

Brisbane venues and villages

The Victoria Park precinct, the Showgrounds village and the Woolloongabba arena — the program's centre of gravity.

  • New venue

    Brisbane Stadium

    Victoria Park, Brisbane

    3/5 · Early works

    New 63,000-seat oval stadium for the ceremonies and athletics; long-term home for cricket and AFL.

    Design:
    COX Architecture, Hassell, Azusa Sekkei
    Delivery:
    Built–SACYR (ECI); John Holland–BESIX Watpac (ECI)
    Main works:
    2027
    Where it stands

    Status. Principal architects appointed; field-of-play and location resolved; design continuing with fan experience, precinct and transport interfaces under development.

    Delivery. Initial works began 1 June 2026. Two joint ventures are in competitive Early Contractor Involvement; the final builder follows the ECI process, with main construction targeted from 2027.

    Outlook. Advancing but high-risk. Site and design leadership are established; cost, transport, park interfaces, ground conditions and schedule integration remain critical.

  • New venue

    National Aquatic Centre

    Spring Hill, Brisbane

    3/5 · Early works

    Elite aquatics complex adjoining Centenary Pool; permanent capacity around 8,000, Games-mode capacity 25,000.

    Design:
    ARM Architecture, NH Architecture, Arkhefield
    Main works:
    2027
    Where it stands

    Status. Design team appointed; design progressing in parallel with contractor procurement.

    Delivery. Site possession and initial works from 1 September 2026. Four contractors shortlisted in July; a two-party ECI and preferred-contractor selection are expected in early 2027.

    Outlook. Advancing. Heritage integration, pools technology, temporary seating, the roof solution and simultaneous procurement and design are the key controls.

  • Village

    Brisbane Showgrounds and Athletes Village

    Bowen Hills, Brisbane

    3/5 · Early works

    Main village for more than 10,000 athletes and officials across about 1,800 apartments, plus a Main Arena uplift and post-Games housing.

    Design:
    Woods Bagot, Cottee Parker, DBI, Plus Studio, Howells
    Delivery:
    Lendlease (partner)
    Where it stands

    Status. Design collective appointed. Early works and arena design activities began after the 2025 Ekka.

    Delivery. Project partners Lendlease and the RNA. Delivery combines precinct works, residential construction, showgrounds operations and conversion planning.

    Outlook. Moderate-to-high interface risk. Strong partners and design mobilisation are positive; the constrained operating site, event calendar and conversion program require detailed staging.

  • Precinct

    Gabba Entertainment and Housing Precinct

    Woolloongabba, Brisbane

    1/5 · Planning

    Proposed 17,000-seat indoor arena inside a housing-dominant redevelopment.

    Where it stands

    Status. Site investigations under way from March 2026; commercial and early-works activity progressing with the private sector.

    Delivery. The 2026–27 budget provides $45.6 million over two years for early works and a competitive market process.

    Outlook. Earlier maturity than the core venues. Private finance, mixed-use feasibility and the Cross River Rail and precinct interfaces are the principal uncertainties.

  • Venue upgrade

    Queensland Tennis Centre

    Tennyson, Brisbane

    1/5 · Planning

    Permanent practice-court and facility upgrades, with Games overlay and accessibility requirements.

    Where it stands

    Status. One of the ten upgraded venues; project validation and investment decisions still required.

    Delivery. No principal delivery contractor publicly confirmed.

    Outlook. Planning stage. Scope control and venue-operation staging will determine schedule pressure.

  • Venue upgrade

    Chandler Sports Precinct program

    Chandler and Belmont, Brisbane

    1/5 · Planning

    Upgrades to the precinct, Brisbane Aquatic Centre, Anna Meares Velodrome and the BMX centre; a new Para Sport Facility; shooting-centre works at Belmont.

    Where it stands

    Status. Projects at differing validation, concept and design stages; the precinct must integrate multiple operating venues and Games overlays.

    Delivery. No complete set of head contractors publicly confirmed.

    Outlook. Portfolio interface risk. Several smaller projects can become schedule-critical if procured late or delivered concurrently inside an active precinct.

South East Queensland venues

New indoor centres, the whitewater venue and the Sunshine Coast stadium — medium projects drawing on the same trades as the flagships.

  • New venue

    Moreton Bay Indoor Sports Centre

    Petrie, Moreton Bay

    3/5 · Early works

    New 12-court multi-use indoor centre for community sport and wheelchair rugby.

    Design:
    Populous
    Main works:
    2027
    Where it stands

    Status. Design and planning progressing; council undertaking early site works.

    Delivery. Construction anticipated from 2027.

    Outlook. Advancing. Large building-services, structural, façade, fit-out and sports-equipment demand north of Brisbane.

  • New venue

    Logan Indoor Sports Centre

    Logan

    3/5 · Early works

    New nine-court accessible centre with a Games capacity of 7,000.

    Where it stands

    Status. Demolition and site-preparation works began in February 2026.

    Delivery. Head contractor not publicly confirmed.

    Outlook. Advancing. Adds southern-Brisbane demand for indoor-sports trades and specialist equipment.

  • New venue

    Redland Whitewater Centre

    Birkdale, Redlands Coast

    2/5 · Procurement

    New specialist whitewater venue.

    Where it stands

    Status. In procurement and delivery; the 2026–27 budget supports commencement alongside the stadium and aquatic centre.

    Delivery. Head contractor not publicly confirmed.

    Outlook. In procurement. Specialist hydraulic, earthworks, concrete, pumping, electrical and water-treatment supply chain.

  • Venue upgrade

    Sunshine Coast Stadium

    Bokarina, Sunshine Coast

    2/5 · Procurement

    Upgrade to host up to 20,000 Games spectators — grandstands, amenities and supporting facilities.

    Design:
    Architectus, HKS
    Main works:
    2027
    Where it stands

    Status. Architect appointed; design continues through 2026.

    Delivery. Early-works contractor EOI closed September 2026; site preparation planned before the end of 2026 and main construction from 2027.

    Outlook. Advancing. Contributes to the Sunshine Coast's simultaneous 2030–31 labour peak and competes with The Wave and housing.

  • New venue

    Sunshine Coast Mountain Bike Centre

    Maroochy River, Sunshine Coast

    2/5 · Procurement

    New permanent mountain-bike venue.

    Where it stands

    Status. Listed by the 2026–27 budget as in procurement and delivery.

    Delivery. Head contractor not confirmed.

    Outlook. In procurement. Civil, landscape, environmental, trail-building and temporary spectator infrastructure.

Regional venues

Cairns, Rockhampton and Toowoomba — Games work that spreads demand beyond the south-east.

  • Venue upgrade

    Barlow Park Stadium

    Cairns

    3/5 · Early works

    New western grandstand, permanent seating from about 1,700 to 5,000, amenities and athlete facilities.

    Design:
    Architectus
    Main works:
    mid-2027
    Where it stands

    Status. Preliminary design under way; delivery-contractor prequalification commenced July 2026.

    Delivery. Services relocation from September 2026; demolition and site preparation late 2026; main construction expected from mid-2027.

    Outlook. Advancing. Regional mobilisation and accommodation add cost, while delivery spreads demand beyond SEQ.

  • Venue upgrade

    Toowoomba Showgrounds

    Toowoomba

    1/5 · Planning

    Equestrian venue upgrade.

    Where it stands

    Status. Part of the authority upgrade program; validation and investment decisions continue.

    Delivery. Contractor not confirmed.

    Outlook. Planning stage. Regional contractor participation reduces SEQ concentration but competes with Toowoomba's broader pipeline.

  • Venue upgrade

    Rockhampton Flatwater Facility

    Fitzroy River, Rockhampton

    1/5 · Planning

    Flatwater venue upgrade on the Fitzroy River.

    Where it stands

    Status. Included in the authority's upgraded-venue portfolio.

    Delivery. Contractor not confirmed.

    Outlook. Planning stage. Marine, river, civil, environmental and temporary-overlay packages.

Transport and rolling stock

Games-enabled rail, road and fleet programs that compete for the same engineers, operators and materials.

  • Rail

    Cross River Rail

    Inner Brisbane

    5/5 · Commissioning

    The backbone project for inner-Brisbane rail capacity: twin tunnels, new underground stations and ETCS signalling.

    Delivery:
    PULSE (Pacific Partnerships, CPB, UGL, DIF, BAM, Ghella); UNITY (CPB, UGL, AECOM, Jacobs); Sequence Alliance (Hitachi Rail, Queensland Rail)
    Where it stands

    Status. Total cost to exceed $19 billion; first passenger services expected in 2029 (QAO, December 2025).

    Delivery. Critical path has shifted from bulk civil works to integration, testing, signalling and operational readiness.

    Outlook. Under delivery. Civil completion without operational readiness is the risk; commissioning is its own critical path.

    Latest
    Cross River Rail is in testing — and the certification phase alone takes two years

  • Rail

    Logan and Gold Coast Faster Rail

    Kuraby to Beenleigh

    3/5 · Early works

    $5.75 billion capacity expansion between Kuraby and Beenleigh, intended for completion before 2032.

    Delivery:
    ActivUs (ACCIONA, CPB Contractors, UGL, SMEC, WSP)
    Where it stands

    Status. Major-works alliance formed; site establishment and early works planned for the first half of 2026.

    Delivery. One of the clearest contractor structures in the pipeline and beyond preliminary procurement.

    Outlook. Under delivery. Competes directly with The Wave and remaining Cross River Rail systems work for specialist rail personnel.

  • Rail

    The Wave (Sunshine Coast rail)

    Beerwah to Caloundra

    3/5 · Early works

    Stage 1: 19 km of dual-track rail, stations at Aura and Caloundra, and Beerwah station upgrades.

    Delivery:
    Beerwah Coast Connect (Georgiou, Hatch, Laing O'Rourke); CoastalTraX (ACCIONA, Georgiou); Alstom and UGL (ETCS)
    Main works:
    early 2027
    Where it stands

    Status. Design and pre-construction packages awarded May 2026; detailed design and investigations continue into 2027.

    Delivery. Major construction expected from early 2027, subject to environmental approvals.

    Outlook. Advancing. Makes the Sunshine Coast a market-capacity hotspot: rail, stadium, village and housing peak together.

  • Rolling stock

    Queensland Train Manufacturing Program

    Torbanlea and Ormeau

    4/5 · Main works

    65 six-car trains, the Torbanlea manufacturing facility and the Ormeau rail facility under a design-build-maintain contract.

    Delivery:
    Downer
    Where it stands

    Status. Supports SEQ growth, Cross River Rail and 2032 readiness.

    Delivery. All 65 trains intended to be on the network by 2032.

    Outlook. Under delivery. Fleet, depot and layover capacity are part of the Games-time transport requirement, not an add-on.

  • Road

    Coomera Connector Stage 1

    Gold Coast

    4/5 · Main works

    New north–south road link improving Gold Coast network resilience, delivered in north, central and south packages.

    Delivery:
    ACCIONA–Georgiou; Seymour Whyte; Fulton Hogan
    Where it stands

    Status. Under construction across the packages.

    Delivery. ACCIONA–Georgiou (north), Seymour Whyte (south main works), Fulton Hogan (central).

    Outlook. Under delivery. Extends demand for bulk earthworks, structures, pavements, plant operators and materials through the pre-Games period.

Announcements

Milestones on the road to 2032

Recent

  1. September 2026

    National Aquatic Centre site works begin; Sunshine Coast Stadium early-works EOI closes; Barlow Park services relocation starts

  2. August 2026

    Victoria Park draft legacy plan released for consultation (3 August to 27 September)

  3. July 2026

    Four contractors shortlisted for the National Aquatic Centre; Barlow Park delivery-contractor prequalification opens

  4. 1 June 2026

    Initial works commence at Brisbane Stadium, Victoria Park

  5. May 2026

    The Wave Stage 1 design and pre-construction contracts awarded

  6. April 2026

    Brisbane Stadium ECI shortlist: Built–SACYR and John Holland–BESIX Watpac

  7. February 2026

    Logan Indoor Sports Centre demolition and site preparation begin

  8. December 2025

    QAO: Cross River Rail to exceed $19 billion, first passenger services expected 2029

  9. August 2025

    Early works and Main Arena design begin at Brisbane Showgrounds after the Ekka

  10. 25 March 2025

    GIICA's 100 Day Review and the 2032 Delivery Plan: venues consolidated at Victoria Park

Ahead

  1. Late 2026

    Barlow Park demolition and site preparation; Sunshine Coast Stadium site preparation

  2. Early 2027

    National Aquatic Centre preferred contractor; The Wave major construction (subject to approvals); final Victoria Park legacy plan

  3. 2027

    Main construction starts at Brisbane Stadium, Moreton Bay Indoor Sports Centre and Sunshine Coast Stadium; Barlow Park from mid-year

  4. 2027–28

    Queensland pipeline peaks near $75 billion; statewide workforce shortfall peaks at up to 35,000 (CSQ)

  5. 2028

    Construction Tech TAFE Centre of Excellence facilities at Caloundra and Moreton Bay due

  6. 2029

    Cross River Rail first passenger services expected

  7. 2030–31

    Games venue-and-village labour demand peaks near 8,000 workers

  8. 2031

    Readiness year: test events, overlay, security and accessibility rehearsals

  9. 23 July 2032

    Brisbane 2032 Olympic Games open (Paralympic Games from 24 August)